Project of execution of water system, fire service and drainage in the underground station of Cais do Sodré

Considering the need to completely remodel the hydraulic networks of Cais do Sodré underground station, we have done the execution project of the water networks, fire service and drainage in an underground station as well as the measurements/estimates of the works to be done.
An inspection and test of the water and drainage networks was carried out followed by a report verifying the conditions of the existing networks.
After analysing the conclusions of the inspection, the construction project was drawn up, which included the water supply network, the fire service network and the rain and waste water drainage network.